Project Info

  • Client: Tridonic
  • Project Date: February 13, 2024

Production Line Move

Enlighten Facility Services were proud to support our Client Tridonic UK Limited in relocating one of its production lines from Dornbirn, Austria, to Durham in the UK. This involved a small team flying out to disassemble the line, allowing it to be palletised and shipped over land.

Whilst the line was in transit, the Durham site was prepared with the installation of a new cable ladder and basket containment systems. The additional steel wire armoured cable feeds were put in place, as well as compressed air and network infrastructure. Upon arrival in the UK, the line was assembled by our team with the assistance of the in-house maintenance department and manufacturer Seho. The work was carried out on time without unpredicted disruptions to site production.